BlockchAIn Digital Infrastructure, Inc. (NYSE AMERICAN: AIB) has announced plans to develop a 50-megawatt data center for Nebius, with an estimated project budget of $800 million. The company stated that customer prepayments are expected to cover its equity requirement for the project, potentially avoiding the need for an equity raise.
The agreement with Nebius is for a 12-year term and includes a firm contract without termination options. According to Chief Executive Officer Jerry Tang, any termination would necessitate full payment. Tang indicated that the customer prepayments will be used for purchase orders and construction costs.
Project Funding and Construction
The total development budget for the data center is approximately $800 million. The anticipated capital structure includes about $560 million in construction debt, $140 million in project-level preferred equity, and roughly $100 million in equity. BlockchAIn Digital Infrastructure expects the customer prepayment to exceed this $100 million equity requirement.

Chief Financial Officer Jolienne Halisky stated that the company has been working with Bank Street on financing preparations. The company projects debt funding to cover 70% of the project budget and is initiating discussions for the preferred equity portion. This preferred investment would occur at the project company or special-purpose-vehicle level.
Tang mentioned that the preferred equity is expected to have an accrual rate in the low teens and an equity kicker of 10% to 20% at the project level. He also clarified that the company does not intend to allow conversion into AIB common stock. Escrowed customer funds can be utilized for purchase orders and construction expenses, characterized by Tang as advance rent.
The first 25 MW data hall is slated for completion approximately 10 months after the receipt of escrow funds. The second 25 MW hall is expected to be finished about 14 months later. Halisky anticipates operational cash flow to commence around the fourth quarter of 2027, coinciding with the first hall’s operational start.

Pricing, Power, and Margins
While the total contract value remains undisclosed due to customer confidentiality, Tang noted that the company’s rate exceeds the range of $1.87 million to $2.16 million per MW per year observed in three comparable contracts. BlockchAIn Digital Infrastructure will maintain its role as the counterparty to the electric service agreement with the utility, with utility costs being passed through to Nebius.
The company projects EBITDA margins of approximately 90%. The $800 million budget translates to about $12 million per MW, based on 65 MW of utility load. Tang cited observed turnkey construction costs ranging from $10 million to $14 million per MW of utility load.
Pipeline and Site Strategy
The Nebius agreement follows a May utility contract for 65 MW over a 15-year term. Preparations for the new data center construction involve decommissioning an existing Bitcoin mining facility at the project site. BlockchAIn Digital Infrastructure also controls four additional sites, representing approximately 280 MW of potential capacity.
Management is focusing on data centers below 100 MW to streamline approval processes and mitigate potential community opposition. The company prefers markets with clear data center regulations and capacity thresholds that define development potential. Tang stated that each data center is leased to a single client.
The company’s objective is to establish a diversified portfolio of eight to 10 clients within the next 24 months. BlockchAIn Digital Infrastructure is engaged in discussions with multiple potential customers for two other sites. The master service agreement with Nebius may allow for the addition of future sites through purchase orders, eliminating the need for complete renegotiation.










